The "Langar-Hall-Roof-Project" started at 17th/18th September
On 17.9.2022 the „Langar-Hall-Roof-Project“ was started with the concreting of the ceiling of the Langar Hall (that building which serves the Sangat and visitors to be able to take there protected from rain or heat his meal).
The work lasted until 18th September at ½ 4 o'clock in the morning, so a total of 18 hours continuously. A great number of helpers came to participate in this selfless service.
Although the work took so long, everybody felt very fresh and many said that it is such an atmosphere like the physical time of Sant Kirpal Singh. When the work was finished nobody wanted to leave, everybody wanted to stay in this special vibration.
The next third of the ceiling will be concreted in the next 1-2 months, the last third will be finished by the end of the year.